Data model

See the plan come together

One working example connecting steel quantities to crew time, crane demand, and measured progress. Try the interactive examples below and follow the sequences in the erection plan. The current example contains 1,505 short tons, 3,087 model pieces and 2,642 planned crane picks.

How the model works One connected production loop

Each step converts the same project information into a more useful planning and control decision.

  1. Project informationModel pieces, tonnage, estimate, milestones and operating constraints.
  2. Work packagesOrganize the project into erection sequences and measurable scopes.
  3. Production unitsConvert model pieces into planned picks and classify the installed work.
  4. Production ratesApply expected rates by work class instead of one uniform tonnage target.
  5. Crew-days and MHCalculate the duration and labor demand required by each sequence.
  6. Time-phased scheduleTime-phase the work using the calculated sequence durations.
  7. Resources and progressLoad crews and cranes, allocate the budget and claim completed gates.

Interactive production examples

Explore the production model

Explore 9 interactive examples, from picks and crew-days to the 4D model, completion gates and earned-value S-curves. Each example connects back to the note that explains it.

Production plan

Sequence quantities, installed units, pick classifications, production rates, crew-days and planned man-hours.

Schedule and resources

Time-phased sequence durations with weekly crane activity and manpower demand.

Progress controls

Budget allocation, completion gates, claimed value, actual hours and earned-value reporting by operation and sequence.

Where this approach has been used

On a large microchip fab project, I worked with the project manager and superintendent to connect model quantities, the existing schedule and agreed completion gates for a box-truss operation. Weekly updates helped the team review progress, manpower needs and inventory for two cranes. The team reused the process in Phase 2. That application focused on scheduling and progress claiming; it did not include all the production tracking explored in these production examples.

Read the field example in Note 08 →