Interactive · Separate work mix from operating performance

What is inside your MH/ton?

Compare the two 12 MH/ton packages, then change picks per ton or man-hours per pick independently. Tonnage and raising-gang staffing stay fixed.

100-ton package · planned picks
Each mark represents 25 planned picks.
Package A reference12.00 MH/ton
Selected package
Shared scale: 0–48 MH/ton
Erection labor
Raising gang duration
Implied erection rate
Fixed sample: 100 tons · 6-person raising gang · 10-hour shifts · erection labor only.