Interactive · Weekly claims and earned credit

Update the weekly claims

Sequence 1 · 1,839 budgeted man-hours (MH)

Update each operation in 25% increments. Claim 100% when its defined scope is complete.

Operation / completion gateBudgetMHEarnedMH
Erect
100%: Sequence erected
537
134
Plumb/bolt
100%: Plumbed and bolted
327
0
Weld
100%: Weld scope complete and accepted
402
0
Deck
100%: Planned deck scope installed
423
0
Detail and closeout
100%: Hand iron, punch and closeout complete
150
0
✓ Complete   ·   ◐ In progress   ·   ○ Not started
Package progress · weighted by budget7.30%
Scopes complete
0 / 5
Budget hours earned
134 MH
Budget hours unearned
1,705 MH
134 earned MH ÷ 1,839 budgeted MH = 7.30%
Hours rounded for display · earned MH are not actual hours spent